Sample change order

Stockroom partition.

Site supervisor’s voice note

“Add a partition in the stockroom. I’ll confirm the length tomorrow.”
Stockroom partition plan The proposed partition, provisionally tagged W3, extends from the inside face of an existing wall to a free end. The dimension marks the length to check on site. The existing hinged door opens into the room. W3 Field verify 4000 mm
Stockroom plan · schematic, not to scale Existing wall New partition

Draft change order

Which wall type should we price?

The voice note gives a room name but leaves the wall type and finish open. An AI estimating agent looks up the adjacent partition in the issued building model, finds the matching finish schedule and attaches both references to the draft. It proposes the following scope for confirmation.

Building model
Wall type W3. Match the adjacent 2.7 m partition, with one layer of gypsum board on each face of the metal studs.
Interior finish schedule
Paint P-02. Warm white eggshell on both faces to match the adjacent walls.

At intake · Length awaiting site confirmation.Draft priced · Project manager review pending.

Reveal the supervisor’s measurementHide the measurement and estimate

“Confirmed on site: 4.0 m long.”

The supervisor confirms the length. Using W3 and P-02 as pricing assumptions, the contractor’s calculator applies the quantities and rates below.

Direct estimate in Canadian dollars
ItemBasisAmount
Board and framing9 sheets, 11 studs, 3 tracks$400
Finish materialsFasteners, tape, compound, corner bead, primer and paint$300
Trade labour18 person-hours × $70/h$1,260
Direct subtotal before tax, rounded$1,960

The project manager confirms the wall assembly and finish, checks the price and records the schedule impact. The contractor then seeks written approval through the project’s change process.

Estimate basis and sources

Scope. The estimate covers one straight, non-load-bearing interior partition without openings on an active project. The direct subtotal excludes delivery, minimum call-out charges, additional general contractor markup and changes to electrical, mechanical or fire protection systems.

Quantities. The two wall faces total 21.6 m². The estimate allows nine 4 ft × 8 ft sheets of ½ in. gypsum board, or 26.8 m² of stock for the faces, exposed end and cuts. The estimator confirms the sheet count against the board layout. Allow one stud at each end and nine between them, at no more than 16 in. on centre. The two 4.0 m track runs use three 10 ft lengths, with offcuts reused. The estimate assumes 3⅝ in. framing and an approved end detail that needs no extra reinforcement.

Materials. Nine sheets at $17.99, eleven 10 ft studs at $16.99 and three 10 ft tracks at $16.99 come to $399.77. Finish materials carry a $300 allowance. The table rounds to the nearest dollar. Retail listings checked on 12 November 2026. Dunbar Lumber gypsum board · Studs and track

Labour. Allow eight person-hours to frame and board, five to tape and finish, and five to prime and paint. The 18 person-hours span several visits. The example assumes a blended billing rate of $70/h. The local guide gives context for carpenter and painter rates. The estimator obtains trade pricing before issuing a quote. Vancouver General Contractors’ 2026 rate guide

Comoving would connect the contractor’s issued documents to its existing estimating template and keep pricing on hold until the field measurement arrives. To test whether the agent earns its place, the estimator could replay past voice notes and compare preparation time and missed scope items with the usual process.

Discuss a construction workflow